In 2013, Red Eléctrica de España completed the construction of 532.05 kilometres of new 400kV electricity transmission lines and 214.68 kilometres of 220kV lines, as published in the 'Spanish Electricity System - Preliminary Report 2013'. At present, the transmission grid has a total of 42,116 kilometres of line.